Saturday, July 25, 2009

Progress - Week of July 20

Decent progress being made. The hickory floors have been installed on the 3rd and 4th floor hallway as well as the library.





The first finish coat of the extension facade went on.





By far the most tedious of the work - the restoration - continues with effort focusing on the exterior doors and the woodwork around the front entrance.





Also started stripping the pocket doors.



The structural work in the rental is just about done and we are waiting for the structural engineer to sign off on the work completed down there before we can remove the temporary shoring.



All the garbage is being relocated to the front portion of the rental and will be carted away this coming Tuesday.



This coming week should be a pretty big week. If I understand correctly (1) the garbage should be removed including the planter in the backyard (2) the dirt pile we've been collecting should be sent offsite (3) the decaying tree in the backyard will be coming down (weather permitting) (4) waterproofing of the new roofs (5) laying out the pex in the master bedroom and master bathroom (6) possibly laying down the new master bathroom floor (7) tile preparations for the rental and 4th floor bathroom.
Check in with us next week to see how we've done.

Saturday, July 18, 2009

Progress - Week of July 13

A very big week. We passed our plumbing inspection. Our stucco guy finished work on the facade which required our neighbor's access and cooperation. DOB came by for a surprise visit after someone lodged a complaint and DOB actually took our side and did not issue a citation. Did I also mention our son was born? That's right...we are writing this post on almost no sleep since Tuesday.

In any event, work continues and some finishing work is taking place. The "floor guy" has also become the "moulding and casing guy". Casings are installed on the 5th floor as well as parts of the 4th floor. Pictures below are of the casings in Tyler's room and the floor going in at the playroom.






Moving to the master floor, the new exterior door was installed which leads from the master bedroom out to the small patio.



On the parlor floor, restoration work continues with the wood casements and wood doors around the front parlor as well as the entryway doors. Although not pictured, the electrical rough-in is almost finished in the extension portion of the parlor floor.






Most of the noticeable work, however, has occured in the rental. First, the tenant's access into their living room was created. In the below picture, the new opening was created on the right and the doorway on the left will be filled in to fill out the kitchen and living room areas.



Here is that perspective from the other side as the tenant enters the apartment from the front.




The tenant's rear exterior door leading to the garden arrived on Thursday and was installed. This door is accessible from the tenant's master bedroom. The demising wall separating the back of the master bedroom from the secondary bedroom will be constructed between the window on the left and the exterior door. You can actually see the structural beam which serves as the demarcation point to demise these rooms.



Oh yeah, more crap is being stockpiled. All those bricks being stacked were salvaged from the various demolition work we've done. It is our intention to find suitable replacement bricks to then infill those holes we created in the front facade where we removed the through-the-wall air conditioning units. In total, we'll need somewhere between 30-40 bricks. I'd say we've amassed about 10 times that amount.



As for the removal of the crap, there is supposedly another dumpster coming on Tuesday to haul this away along with the various junk still remaining in the backyard. In what might be the penultimate dumpster, the contractor is supposed to remove this hideous and incredibly awkward "planter" which disgraces the landscape in the backyard. Matt will be particularly pleased when this is removed because it will then allow for the arborist to come and remove a very large and very decaying tree from the backyward.

Back to the rental construction, the temporary shoring is slowly being removed as the new steel beam in the rental is installed. Again, once completed this will open up the space in the rental master bedroom.



Onto the new facde on the extension. Besides the work being completed which required our neighbor to cooperate, the basecoat has been fully applied and the extension looks like this now.





The finish coat should go on next week (weather permitting) whereupon we'll take a few photos of the finished product and give you a little before and after comparison.

I also wanted to show a few shots of the front of the house, particularly now that the tree in the front has been pruned back some. Before the tree was thinned out, it was literally growing towards the front door and into the house.






On tap for next week...hickory floor installation on the fourth and third floor landing areas, new floors on the third floor in the library and possibly the master bedroom (if the radiant floors are installed), tile preparation for the bathrooms, finishing off the new facade at the extension, finishing off the structural work in the rental as well as completing the rough-ins and framing.

Sunday, July 12, 2009

Progress - Week of July 6

Apologies for not a lot of pictures...the batteries in the camera were dying.

Over the past week we made ok progress. The plumber finished installing the radiators and started laying out the pex for the radiant floors in the master bedroom and bathroom. I believe the hope is to have our plumbing inspection this week.


In the rental, unfortunately none of the remaining structural work has commenced, so it looks like that will bleed into this coming week.

We shored up one of the party walls in the kitchen but we still need to re-pack the brick in one other location.

The floor guy has put down the floor in the second bedroom on the 4th floor (picture below) but we still need to lay the white oak in the playroom. The hickory was ordered last week and that may be on site this week although I am not sure it will be installed.


The basecoat of the new facade on the extension has been applied and we may have the finish coat on there by the end of this week.

A tree pruner came to the house today and also took down a lot of the overgrowth in the backyard as well as some strategic pruning in the front.


Now for the pictures...

We had two arborists selectively trimming back the trees in the backyard. For the maple in the back, these guys climbed the tree up to about 30 feet high on branches which frankly did not look very thick. After they were done, it was amazing how much light was actually coming through and it also revealed how crappy our fence is. Before any environmentalists go crazy with our apparent de-forestation of Brooklyn Heights, selective harvesting of trees will promote the growth of healthy and potentially sunlight-starved trees. As for the clippings and cuttings, we turned the branches into clubs and will use them to maim baby seals.


The restoration effort continues. We've moved from a chemical paint-removal application to heat. Below is one of the doors leading into the parlor from the hallway.


The doors are starting to get hung. These 5-panel doors are on the master floor (3rd floor).


A shot from the inside of the master bedroom.



And a shot of the 4th floor where we have a 3-panel door.



The new floor in the second bedroom...


I hate to project what will be on tap for the coming week but I suspect a new member of the Karp clan.

Sunday, July 5, 2009

Progress - Week of June 29

Work continues albeit at a less noticeable pace. Besides the work taking place inside the project, we are spending a lot of time behind the scenes finalizing lighting and hardware and putting in orders for other finish materials.

First, the container arrived Tuesday and the parlor is once again free of detritus for at least another few weeks. Hurray! More landfill!



Good thing we moved out the garbage because the base mouldings and window and door casings arrived. The white oak order was also delivered and is partially installed. The attic is pretty much done...





Also, the wood restoration is moving. The entry doors from the vestibule are looking better with each passing day. Depending upon the condition, we will either repaint the wood or (hopefully) stain the wood in a darker, mahogany finish to conceal some of the imperfections left in the wood given the paint stripping and decades of neglect.





The plumber has run the pex tubing for the hot water to the radiators.



Also, the rear door leading off the new kitchen was installed.



On tap for this week: the last of the structural work in the rental and the kitchen, finish the installation of the white oak floors, framing out of the master bathroom.