Sunday, June 28, 2009

Progress - Week of June 22

Progress being made on the exterior facade at the extension...tyvek wrap, foam boards and windows are installed...








A look at the kitchen from the inside with the windows installed as well as a bit more framing...





The beginning of the restoration work...stripping of the multiple layers of paint from the original doors. To be determined if we are going to repaint or stain the doors. A lot depends on the condition.



New electrical panels installed...this is the one that will serve the main house.



New subfloor in the attic. We had to rip out the old subfloor as there was a 6" elevation difference on the floor. Hope that the finished floor will be on site this week.



The garbage is still there...container coming on Tuesday. Yippee!



In store for this week (besides garbage removal)...phase I of finish flooring onsite, structural work in the rental, repacking the brick in the party wall, and the millworker is coming to take field measurements for the kitchen cabinets.

1 comment:

  1. My room in the attic is coming along nicely! Let me know when you are ready for me to come pick the paint ;) Seriously, congrats on the progress. You are going to definitely enjoy evening glasses of wine on that balcony after the kiddos are in bed.