Monday, May 25, 2009

Progress - Week of May 18

Work continues....

Progress for the rear extension below. Difficult to see, but the steel structure is up through the second floor and the first column is in place for the third floor (which is will be the master bathroom).



This is the interior shot of what will be the kitchen. The door frame on the right will lead to the stairs down to the garden.






Just so you recall, the space used to look like this six weeks ago....





Finally, a few interiors of the parlor now that the area has been cleaned up a bit.





We neglected to capture in photograph, but also all new windows (except for those in the extension) are installed and our first order of interior doors arrived.

Stay tuned.